PROGRESS CORNER
SEPTEMBER 2019:
EISENHOWER MIDDLE SCHOOL MAJOR 2017 FACILITY BOND PROJECTS
44% Complete
Brick veneer is being installed on the east & south sides
Installation of CMU in kitchen area
Tiling started in restrooms
Joist & columns in progress for commons area
Furniture 95% design review
SAFE ROOMS (*PHASE 1)
Almor West: Substantial Completion
Carriage Hills: Substantial Completion
Crosby Park: Substantial Completion
Edison: Substantial Completion
Hugh Bish: Substantial Completion
Sullivan Village: Substantial Completion
Woodland Hills: Substantial Completion
Whittier: In-Progress
ATHLETIC TRACK RESURFACING:
MacArthur High School: PROJECT COMPLETE
Eisenhower High School: In-Progress
Lawton High School: In-Progress
WINDOW PROJECTS:
Eisenhower High School: PROJECT COMPLETE
Lawton High School: Awaiting completion of punch list items
MacArthur High School: PROJECT COMPLETE
HVAC PROJECTS:
Adams Elementary, Almor West Elementary, Lincoln Elementary, MacArthur Middle, Tomlinson Middle and Woodland Hills: PROJECTS COMPLETE
ROOF PROJECTS:
Lawton High School, Tomlinson Middle School, John Adams Elementary, Carriage Hills Elementary, Edison:
PROJECTS COMPLETE
MHS CAFETERIA PROJECTS:
Awaiting O&M manuals and completion of punch list items
Fire Alarm Upgrade: In-Progress
MHS HVAC AUDITORIUM, GYM & ADMIN PROJECT:
Contract approved by Board in August
95% Review 9/19/19
Advertise bids 10/03/19
EQUIPMENT, TECHNOLOGY & FURNITURE:
Classroom furniture ordered with summer delivery
2700 Chromebooks deployed to 6 secondary sites (EHS, LHS, MHS, MMS, CMS, EMS)
Tomlinson Middle School is already a 1:1 site with iPads, and that was made possible through a Federal Grant
Replacement of the projector and Smartboard setups with 4K 65” Interactive Flat Panel (a touchscreen TV) for 129 classrooms throughout the district
Band Instruments purchased
Band Uniforms purchased for EHS, LHS, & MHS
Flooring, carpeting, gym wall pads, ceiling fans, lighting, mini-blinds and air conditioning upgrades & purchases
Instructional software licenses, books & materials purchased district-wide
Textbooks purchased & Textbook Software purchased
Transportation GPS system & cameras
Library books & supplies
ELEMENTARY GYM REPAIRS:
Almor West: Substantial Completion
Carriage Hills & Crosby Park: Permits approved by City. Construction awaiting PO
FENCING:
Fencing studies started
District staff members have worked extremely hard to move as fast as possible. We owe it to you to deliver on this bond and to keep you informed. (*View SIP Project Updates)